Library Parking Lot Reconstruction

Library Parking Lot Reconstruction

Want to be kept up to date on the progress of this project? Sign up here to receive regular project updates via E-MAIL or directly to your phone via TEXT message.  


Week 12 Update
Friday, December 17, 2021

Copenhaver Construction placed aggregate in the west and central areas of the site for final compaction, and backfilled behind the barrier curb.  Brick pathways in the islands were completed.  New frames and lids were installed on the inlets and adjusted to final grade. Brick paver installation was completed and pavement markings were installed.  Site clean-up was completed and signage is being re-installed.

The parking lot officially re-opened on Friday, December 17 at 12:00 PM.

Landscaping is scheduled for Spring 2022.

Library W 12 1 Library W 12 2 Library W 12 3
     
 Aggregate placement on brick pavers for final compaction Cutting brick pavers for storage areas Completion of brick pavers in the west area of the site
 

Week 11 Update

Week 10 Update

Week 9 Update

Week 8 Update

Week 7 Update

Week 6 Update

Week 5 Update

Week 4 Update

Week 3 Update

Week 2 Update

Week 1 Update

Parking Alternatives

Project Description and Schedule